How to do a take-off per m² (method + example)
Updated July 2026
A take-off is the costed list of everything a site needs: line items, quantities, units. Done well, it protects your margin. Here is the method in 5 steps, with an area-calculation example and the pitfalls to avoid.
What is a take-off?
The take-off is the count of all the works on a site with their quantities. It's the backbone of the quote: each line item (demolition, masonry, tiling…) is listed with its quantity and unit.
The stake is simple: an underestimated quantity, and the margin evaporates. A rigorous take-off, and you price right.
The units that matter
- m² for areas (tiling, paint, plaster…)
- m³ for volumes (concrete, earthworks…)
- m (linear metre) for lengths (skirting, cornices, pipes…)
- piece/unit for countable elements (doors, sockets…)
- kg or tonne for weights (steel…); lump sum for a whole
The method in 5 steps
- 1Take the dimensions from the plan (or on site): lengths, widths, heights.
- 2Break the site into clear line items, from structure to finishes.
- 3Compute the quantities: areas (L × w), volumes (L × w × h), lengths.
- 4Add waste and offcuts (a percentage depending on the material).
- 5Carry each quantity into the quote, with its unit and price.
Example: calculating an area
A room of 4 m × 5 m is 20 m² of floor. For tiling, you plan for offcuts (often ~10%): so you order about 22 m² to cover 20 m² for real.
For wall paint, you calculate the wall area instead (perimeter × height), deducting large openings where relevant.
Common pitfalls
- Forgetting offcuts and material waste
- Forgetting a line item (preparation, protection, waste removal)
- Confusing net area and area to order
- Using the wrong unit (billing per m² what counts per linear metre)
From take-off to quote
Each take-off line is multiplied by its unit price (the cost), then by a coefficient covering overheads and profit, to get the selling price. Hence the value of a well-kept price catalogue — so you don't start from scratch each time.
Frequently asked questions
What is the difference between a take-off and a quote?+
The take-off lists the quantities (how many m², m³…). The quote adds the prices and terms. The take-off is the calculation basis of the quote.
Do you always have to add offcuts?+
For cut materials (tiles, flooring, boards…), yes: a waste percentage avoids running short. The rate depends on the material and complexity.
What unit for paint?+
The m² of surface to paint (walls and/or ceiling), deducting large openings. The number of coats is taken into account for paint quantities.
Can you do a take-off from a photo?+
AI tools help identify line items from a site photo; useful to go fast, but an estimate to be confirmed by a real measurement remains recommended.
Read also
A compliant construction quote: the template and detailsCost, margin, coefficient: pricing rightThe CCTB explained simplyFrom plan to take-off, in minutes
Afrimo reads your plans (and your site photos), suggests the line items and computes the quantities; VAT applies and the quote is generated — in FR/NL/EN.
This article is informational. Methods and waste rates depend on materials and good practice: adapt them to your situation.